The activity

The activity

Primary and secondary roads: widening, strengthening and formation of new roadbeds.

Share of works completed since 1970 · Roads and motorways

32%

Breakdown of works by business line

In figures

Roads in figures

Quantities delivered

of roads and motorways
1,447 km

Daily production capacity

Asphalt mix production
4,500 t
Transport and storage of bitumen binders
500 t

Group companies

Group companies

  • Multi-infrastructure works

    ELTG

    General contracting: roads, motorways, urban roads and marine works

  • Multi-infrastructure works

    LSP

    Road markings and road signs

Projects

Projects in this category

18 contracts completed

Projects in this category
Photos Project Location Quantities Contract value Client
Construction of the road linking Bouizakarne to Tan-Tan Construction of the road linking Bouizakarne to Tan-Tan (PK 41 & PK 141)AG 76/87 Bouizakarne – Tan-Tan 101 km Ministry of Public Works & Transport
Boujdour – Dakhla road Construction of the Boujdour – Dakhla roadSH 12/86 & SH 38/85 Moroccan Sahara 163 km & 202 km 180 + 290 million DHS Ministry of Public Works & Transport
Construction of the Tan-Tan – Tan-Tan Plage road Construction of the Tan-Tan – Tan-Tan Plage roadAG 79/83 Tan-Tan 36 km Ministry of Public Works & Transport
Construction of the Guelmim – Kassabi road Construction of the Guelmim – Kassabi roadAG 71/86 Guelmim 27 km Ministry of Public Works & Transport
Widening and strengthening of roads in the Meknès region Widening and strengthening of roads in the Meknès regionME 8/9 ; 41/91 & 40/91 Meknès region 67 km Ministry of Public Works & Transport
Widening and pavement strengthening of trunk road RP 1 Taza – Guercif Widening and pavement strengthening of trunk road RP 1 Taza – GuercifTZ 213/86 Taza – Guercif 43 km Ministry of Public Works & Transport
Construction of new carriageways between Arazane and Aoulouz Construction of new carriageways between Arazane and AoulouzAG 16/90 Arazane – Aoulouz 68 km Ministry of Public Works & Transport
Formation of the RP 30 roadbed, lots 1 & 2 (earthworks), Akka – Tata Formation of the RP 30 roadbed, lots 1 & 2 (earthworks), Akka – TataTI 69/80 Akka – Tata 77 km Ministry of Public Works & Transport
Construction and widening of the Agadir – Tiznit road Construction and widening of the Agadir – Tiznit roadTI 37/82 Agadir – Tiznit 29 km Ministry of Public Works & Transport
Construction of the road linking Ouarzazate to Tata Construction of the road linking Ouarzazate to TataAO 102/89 Ouarzazate – Tata 63 km Ministry of Public Works & Transport
Construction of the access roads to the El Hachef dam Construction of the access roads to the El Hachef damTA 24/90 Tanger 13 km Ministry of Public Works & Transport
Illustrative photo — civil engineering structure Construction of the access roads to the Oued Yssen damAG 13/79 Agadir region 12 km Ministry of Public Works & Transport
Illustrative photo — road construction site Construction of the access roads to the Aït Tachouarite damMA 06/81 Marrakech region 17 km Ministry of Public Works & Transport
Khouribga (16 km) Widening and strengthening — PGR (General Road Programme)Marché cadre Khouribga, Béni Mellal, Marrakech, Rabat and Settat regions 210 km Ministry of Public Works & Transport
Tarhjijte – Tata road Construction of the road linking Tarhjijte to TataAG 64/88 Tarhjijte – Tata 75 km Ministry of Public Works & Transport
Construction of the road linking Ouarzazate to Tata Construction of the road linking Ouarzazate to TataAG 33/99 Ouarzazate – Tata 63 km Ministry of Public Works & Transport
National road, Tiznit – Tafraout section National road, Tiznit – Tafraout section Tiznit – Tafraout 33 km
National road, Agadir – Chichaoua section National road, Agadir – Chichaoua section Agadir – Chichaoua 79 km

All projects